1
Chat with us?

THE GOVERNMENT GUIDANCE ON FORMULATION OF APPRAISAL DOSSIER FOR PUBLIC INVESTMENT PROJECT

This content is approved by the Government on the Decree No. 40/2020/ND-CP on detailing and guiding the implementation of a number of Articles of the Law on Public Investment on April 06, 2020.

Accordingly, the appraisal dossier for public investment project without construction component shall include the following documents:

First, a written proposal for appraisal of the project, with: The necessity of investment in the project; objectives and principal contents of the feasibility study report of the project; proposal for competent authorities to decide on the public investment program;

Second, the feasibility study report of the project as prescribed in Article 44 of the Law on Public Investment;

Third, the reports of the Vietnam Fatherland Front Committees at all levels summarizing opinions of residents in the place where the project is to be implemented for projects as prescribed in Article 74 of the Law on Public Investment.

Fourth, other relevant documents serving the appraisal of public investment projects (if any). And the dossier for appraisal of a public investment project with construction components must comply with the law on construction, and contain opinions of residents and other relevant law regulations. The number of appraisal dossiers sent to the Appraisal Council or the agency in charge of appraisal is 10 sets.

In addition, order and procedures for decision on investment policy on programs and projects that use capital from lawful revenue sources of state agencies and public non-business units for investment...

This Decree takes effect from the date of its signing.